Printrelease packaging
Provision of the print data and entry of the delivery date.
BM - All-in-One INT
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - All-in-One NAT
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Allowlist
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Druckerwechsel
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Fast Lane 1
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Fast Lane 2
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Relaunch Design
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
BM - Tray
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
Moreover the prepress agency receives flag “Celum Upload Packaging”, creates the data packet for Celum, loads the data into Wave and confirms the flag.
LF
Must maintain the field delivery date within 10 working days.
The status changes automatically from S7 to S8 if the following conditions are met:
▪ Delivery date is entered by LF
▪ Data provision flag was set to “Green” by Repro
▪ Celum flag incl. Response successful green
Information about print release is sent to the responsible purchaser.
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
QM - Dekla Anpassung INT
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
LF
see status 9
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
QM - Dekla Anpassung NAT
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
LF
see status 9
8 – Check of production samples
Once production samples are received from the supplier, they are tested.
QM - Allowlist
Repro
–
LF
–
see status 9
QM - Fast Lane 3
Repro
Creates print data based on the approved layouts and provides them via download link. Afterwards, the flag (task) “Data delivery” is confirmed.
Data delivery
LF
see status 9
8 – Check of production samples
Once production samples are received from the supplier, they are tested.