Packaging Structure
The package is created, loaded into Wave and the APL is started.
BM - All-in-One INT
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option to have the front layout checked in advance by BM via a flag:
Front structure
And/or approve the proof also by flag (field selection “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
BM
Brand management can reject the flag with correction in Dalim (RED “New request for front set-up”) or confirm (GREEN “Front set-up approved”).
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - All-in-One NAT
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option to have the front layout checked in advance by BM via a flag:
Front structure
And/or approve the proof also by flag (field selection “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
BM
Brand management can reject the flag with correction in Dalim (RED “New request for front set-up”) or confirm (GREEN “Front set-up approved”).
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Allowlist
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option to have the front layout checked in advance by BM via a flag:
Front structure
And/or approve the proof also by flag (field selection “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
BM
Brand management can reject the flag with correction in Dalim (RED “New request for front set-up”) or confirm (GREEN “Front set-up approved”).
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Druckerwechsel
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option of approving the proof via a flag (field selection à “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Fast Lane 1
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option of approving the proof via a flag (field selection à “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Fast Lane 2
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option of approving the proof via a flag (field selection à “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Fast Lane 4 - Umsetzung durch Lieferant
LF
sets up the layout on the basis of the product specification part 2 uploaded by quality management in the Files tab.
Requirements: https://kl-packaging.schwarz/wp-content/uploads/2025/03/ENG_DE_layoutcreation_Fastlane4.pdf
For labels with German or native language, the assembly timing is 5 working days.
If Eastern European languages are used that cannot be checked by native speakers, a translation and checking by a testing institute is necessary (timing 12 days including layout of the label).
The following flag (task) is triggered for this purpose:
PI check requested (timing 4 working days)
As soon as the assignment has taken place, the first flag “Assignment Translation” is confirmed and the follow-up flag (task) is triggered:
Upload PI certificate (timing 8 working days)
The certificate and PDF of the layout must be uploaded in the Order details tab under Supplier.
Then the flag “upload certificate / test report” must be confirmed and the status must be changed to status 4.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Relaunch Design
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency has the option to have the front layout checked in advance by BM via a flag:
Front structure
And/or approve the proof also by flag (field selection “Proof yes”).
Confirmation flag when proof is final.
Packaging proof
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
BM
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
BM - Tray
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
QM - Dekla Anpassung INT
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
QM - Dekla Anpassung NAT
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
QM - Allowlist
Repro
Prepress agency builds the layout based on the briefing and the upload documents.
Prepress agency uploads the KVA and confirms upload “KVA uploaded”.
KVA upload
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.
QM - Fast Lane 3
LF
builds the thermal label based on the product specification part 2 uploaded by the Quality Management in the files tab.
For labels with German or native language, the timing for the label creation is 5 business days.
If Eastern European languages are applied, which cannot be checked by native speakers, a translation and check from a testing institute is necessary (timing 10 days including label creation).
For this the following flag is triggered:
PI Check requested (Timing 4 business days)
As soon as the commissioning has taken place, the first flag “Request translation” is confirmed and the follow-up flag (task) is triggered:
Upload PI certificate (Timing 8 business days)
Overview of possible timings:
Timing for single language, no translation (translation can be done by a native speaker), marketability testing from a native speaker: 5 business days.
Timing for single language, with translation and testing by a testing institute: 17 workdays
Timing Eastern European label with multiple languages, with translation and testing by testing institute: 22 working days
Upload of certificate and PDF of thermal label must be done in Order Detail tab under Supplier. Afterwards, the flag “Upload certificate/test report” must be confirmed and a status change to status 4 must be made.
2 – Data collection incomplete
All necessary data and information is organized, loaded into Wave if necessary, and checked for completeness.
4 – Packaging approval
The packaging buildup is checked in the APL, the status is automatically changed after completion.